Time approval - Implementation
Prerequisites
Activity codes
The following activity codes (sorted by type) may have an impact on the way the function operates:
Dependent activity codes
These codes are never entered in folder management, because their value is calculated:
PJMSA (PJM & Sales modules enabled)
Functional
PJM:
Project management
Sizing
ANA:
No. of analytical dimensions
PJMTI:
Time entry
General parameters
The following general parameters may change the way the function is working:
Common Data
PJMTIMENT (defined at level Site): Time entry control phase
Authorizations
An authorization can be granted for this function to limit the processes to a company or a site.
The following options can be activated or deactivated for each user:
Validate
Control
Approve
Reject
Tables used
No table is used by this function.