UPDSCD: Scheduling update

Use this entry point to authorize (or not) the scheduling re-calculation following an operation tracking creation.

Context and operating mode

Transaction

There is one transaction in progress.

Log file

There is an open log file.

 Use

Set GPE to 1 to prevent a re-calculation of the scheduling. 

Open tables

In the table below, the significant content flag indicates that the content is in phase with the context.

Table

Significant content

Table Title

MFGHEADTRK

Yes

Tracking header

MFGOPETRK

No

Operation tracking

 

CUSSRT: Specific sort for the material grid

Use this entry point to take over at the end of the material grid loading, just before the recordings are sorted, in order for example to sort the lines according to an order that was not planned in standard mode.

Setting the GPE variable to the value 1 is used to not carry out the standard sort.

Context and operating mode

Transaction

There is one transaction in progress.

Log file

There is an open log file.

 Use

Set GPE to 1 to prevent the standard sorting of components. 

Open tables

In the table below, the significant content flag indicates that the content is in phase with the context.

Table

Significant content

Table Title

MFGHEADTRK

Yes

Tracking header

MFGMATTRK

No

Material tracking

 

AFFTRA: Possibility not to display the log file

Use this entry point to delete the display of the generated log file on tracking plan validation.

The GPE global variable must be reset to 0 to prevent the display.

Context and operating mode

Transaction

There is no transaction in progress.

Log file

There is an open log file.