Resynch weighing plan flag
Use this function to resynchronize flags on the weighing plan if work orders become locked as a result of a system error.
You can run this function as required if locks in the system prevent you from closing work orders after the components have been weighed.
Prerequisites
Refer to documentation Implementation
Screen management
The Resynch weighing plan flag function displays an initial screen into which you enter your selection (or filtering) criteria.
The System log displays the results of the run.
Entry screen
Use this screen to define the production site from which the work orders are to be processed and the dates the system errors occurred.
Selection criteria
Production site (field MFGFCY) |
Type in or select the production site from which the work orders are to be processed. |
Date weighed (field CBTDATSTR) |
To include all dates, leave this field blank. To include only selected dates, enter the required start date. |
field CBTDATEND |
To include all dates, leave this field blank. To include only selected dates, enter the required end date. |