Financial snapshot extraction

Use this function to obtain real-time top-level financial overviews, snapshots, of one or multiple projects for one company, or for all companies.

A financial snapshot is based on the actual financial status of a project relative to its budgets. It provides similar figures to those provided for a project financial overview.

To extract data for a single project you can access this functionality directly from that project.

You can only use this function if snapshot headers exist for the required projects. Refer to the Financial snapshots function documentation which describes the "snapshot header" creation process in detail.

Prerequisites

SEEREFERTTO Refer to documentation Implementation

Screen management

The Financial snapshot extraction function contains a single screen in which you define your snapshot extraction selection criteria.

Financial snapshots function (GESPJMSNP) to view the extracted data.

Entry screen

You use this screen to filter or select the projects to be included in the financial extraction run.

A "snapshot header" sets the parameters for a financial extraction. A snapshot header is a prerequisite to running a snapshot extraction. It comprises the project code, the financial view to be extracted, and the unit and currency to be used each time the data extraction is requested.

You can use this function to extract project financial data as, and when required once a snapshot header has been created.

Extracted snapshot data is added to the list of snapshots in the Financial snapshots function (GESPJMSNP).

Each time you extract snapshot data the Financial status sections of the associated project and the cost structure is synchronized with the extracted data if the FINOVERSYN-Updated fin. status/snapshot parameter (TC chapter, PJM group) is set to Yes and the Revenue recognition checkbox (REVRECFLG field) is selected for a snapshot header. If the ESTPRGSYNC-Updated est. progress/snapshot parameter (TC chapter, PJM group) is set to Yes, the estimated progress percentage of the project, the project budget, and the operational task (Estimated progress (%) fields) are updated.

As a snapshot is real time, each new snapshot you obtain overwrites a previous snapshot created on the same date. Similarly, each new snapshot you obtain refreshes 1: the project and cost structure financial status, if the FINOVERSYN-Updated fin. status/snapshot parameter (TC chapter, PJM group) is set to Yes and the Revenue recognition checkbox (REVRECFLG field) is selected in the snapshot header; 2: the estimated total revenue for the project, if the ESTREVSYNC-Updated est. revenue/snapshot parameter (TC chapter, PJM group) is set to Yes and the Revenue recognition checkbox is selected in the snapshot header; 3: the estimated progress percentage of the project, the project budget, and the operational task, if the ESTPRGSYNC-Updated est. progress/snapshot parameter (TC chapter, PJM group) is set to Yes.

Batch task

This function can be run in batch mode, but no dedicated standard task is delivered to run it.

Error messages

The only error messages are the generic ones.

Tables used