This parameter is used in the MRP and MPS processes. You use it to set up the end date of late suggestions:

First possible date - The end date for the late suggestions is the first available date (Reference date for calculation if there is no firm horizon or End date of firm horizon + 1, for example).

First possible date + leadtime - The end date of the late suggestions is calculated based on the reorder lead time (Reference date for calculation + lead time or End date of firm horizon + lead time, for example).

Level of localization/Global variable

This parameter is defined at the level Site. It belongs to Chapter STO (Inventory) and the Group REA (Reorder), The following parameters are also associated with this chapter and group :

The global variable GLATSUGDAT is associated with it.

Functions concerned

The following functions are associated with this parameter :

  Manufacturing > Planning > MPS processing

  Stock > Reorders > MRP processing

  Manufacturing > Planning > MRP processing