Integrate allocated qty
This parameter is used when running the MRP (Manufacturing Resource Planning) and the quantity allocated to a sales order line is above the ordered quantity.
You use it to indicate if the MRP must include the allocated quantity or not:
Yes - The MRP processes the allocated quantity as a demand coming from the sales order. For example, if the allocated quantity on the order line is for 15 products but the ordered quantity is for 10 products, the MRP will process a demand for 15 products for this sales order.
No - The MRP only processes the ordered quantity and ignores the allocated quantity.
Level of localization/Global variable
This parameter is defined at the level Site. It belongs to Chapter STO (Inventory) and the Group REA (Reorder), The following parameters are also associated with this chapter and group :
- LATSUGDAT (End date of late suggestions)
- MPSDYNCOV (MPS seasonalized coverage)
- MPSDYNSAF (MPS seasonalized safety stock)
- MRPDYNCOV (MRP seasonalized coverage)
- MRPDYNSAF (MRP seasonalized safety stock)
No global variable is associated with it.
Functions impacted
The following functions are associated with this parameter :
Stock > Reorders > MRP processing
Manufacturing > Planning > MRP processing