Stock purge security
Use this parameter to enter the security lead time to be applied for purging stock movements. This processing applies to the movements earlier than a specific date, which is calculated as follows: todays's date - security lead time.
Enter the lead time in months.
When running the processing, you can only update the calculated date with an earlier date.
Level of localization/Global variable
This parameter is defined at the level Site. It belongs to Chapter STO (Inventory) and the Group PUR (Purges), The following parameters are also associated with this chapter and group :
- MARPURLOT (Lot purge security in months)
- MARPURSER (Serial number purge security)
- MARPURTRK (Traceability purge security)
No global variable is associated with it.
Associated functions
The following functions are associated with this parameter :
Stock > Periodic processing > Purge > Stock transactions