This function is used in the reconciliation of all the material weighed on a weigh station for a works order.
The reconciliation can be carried out once all the materials to be weighed on the weigh station have been weighed.
These materials in production can be weighed after the reconciliation.
A partial reconciliation is not possible, if a reconciliation is started it must be competed. If not, all the reconciliations for the works order are deleted.
Refer to documentation Implementation
Presentation
Product : by right click there is the possibility to access the inquiries :
Operation number : by right click there is the possibility to access the inquiries :
Close
Fields
The following fields are present on this tab :
Order
|
The production site associated with the user is proposed by default. It can be modified by another site authorized for the operator, depending on its authorizations. |
|
Number of the order to reconcile. |
|
  |
|
  |
|
  |
|
  |
Grid Components
|
  |
|
  |
|
Number of the component to reconcile. |
|
The phase number to be reconciled. |
|
Lot number decreased upon weighing. |
|
Weight obtained. |
|
  |
|
  |
|
  |
|
  |
|
  |
|
  |
Close
This button is activated if a record to be reconciled is found |
This button is activated if at least one reconciliation has been made for the order number. |