This function is used to analyze all the recordings of planned or firm load WIP and compare them to the various files in the database in order to detect and correct any desynchronizations.
Refer to documentation Implementation
Presentation
This function analyzes all the recordings of the OPERATIONS table corresponding to planned or firm WIP (the suggested WIP is not considered) relating to the production site for which the processing has been carried out.
For each WIP, the system tests any possible anomalies, such as:
Automatic correction: it is possible to perform a re-synchronization simulation that does not update the WIP, but provides a log of the detected anomalies. Activating the "Automatic correction" setup makes it possible to perform the updates further to the detected anomalies.
Recalculation of the Work Center Totals: it is possible to let the system recalculate the planned and achieved time totals and update them on the work centers, should a desynchronization be detected.
Close
Fields
The following fields are present on this tab :
Selection criteria
|
The production site associated with the user is proposed by default. It can be modified by another site authorized for the operator, depending on its authorizations. |
Block number 2
|
  |
|
This parameter, if active, makes it possible to carry out the appropriate corrections automatically. |
|
If active, this setup makes it possible to recalculate |