Use this function to resynchronize flags on the weighing plan if work orders become locked as a result of a system error.
You can run this function as required if locks in the system prevent you from closing work orders after the components have been weighed.
Refer to documentation Implementation
The Resynch weighing plan flag function displays an initial screen into which you enter your selection (or filtering) criteria.
The System log displays the results of the run.
Presentation
Use this screen to define the production site from which the work orders are to be processed and the dates the system errors occurred.
Close
Fields
The following fields are present on this tab :
Selection criteria
|
Type in or select the production site from which the work orders are to be processed. |
|
To include all dates, leave this field blank. To include only selected dates, enter the required start date. |
|
To include all dates, leave this field blank. To include only selected dates, enter the required end date. |
Close