Stock >  Reorders >  MRP processing >  MRP processing - Implementation  

Display all Hide all

Prerequisites

Other prerequisites

Products must be assigned the Reorder mode 'By MRP' to be considered (requirements or resources) by the MRP calculation run.

The following parameters must be assigned:

  • Scheduling parameter (see the Scheduling documentation)
  • MRP parameters (see the MRP documentation)
  • Reorder policy applied to the product-site record (see the Reorder policy documentation)
  • Management rules for the product-site record (see the Product-site documentation)

General parameters

The following general parameters may change the way the function is working :

Manufacturing

  DEFDIH (defined at level Site) :  Default schedule

  GPERCOMP (defined at level Site) : % LT reduction default

  GTPSCOMP (defined at level Site) : Slack time compression

  OPEEFFAPP (defined at level Site) : Efficiency application

  WSTEFFINH (defined at level Folder) : Work center efficiency history

Inventory

  FIRWRKDAY (defined at level Site) : First work day of week

  LATSUGDAT (defined at level Site) : End date of late suggestions

  MAXALLQTY (defined at level Site) : Integrate allocated qty

  MRPDYNCOV (defined at level Site) : MRP seasonalized coverage

  MRPDYNSAF (defined at level Site) : MRP seasonalized safety stock

  MRPRECOVST (defined at level Site) : MRP reduce coverage stock

  STODISSCO (defined at level Folder) : Subcontract stock

Authorizations

An authorization can be granted for this function to limit the processes to a company or a site.

Tables used

The following tables are implemented by the function :

Table

Table description

CBNDET [CBD]

MRP detail

CBNHEA [CBH]

MRP processing

CBNWRK [CBW]

MRP workfile

ORDERS [ORD]

WIP