This report describes the results of the production anayses for the resource dimension view and more particularly the resource yield (main work center and labor work center).
(see the Production analyses and Product analysis printing documentations)
This report presents by bite and by work center the sum of quantities (planned and actual) and the reject reported at the level of each work center, an indication of the average yield and the average reject.
The results are totalled at the level of each work center.
The display presents:
The sum of the rejects represents the reject quantity reported at operation tracking level
The system submits the average yield and the average reject, and it stipulates the number of operations achieved on the work center.
Parameter |
Parameter title |
Type |
---|---|---|
wcrfcydeb |
Plant range |
|
wcrdeb |
Work center group range |
|
wstdeb |
Work center range |
WST |
enddat |
Analysis end date |
D |
impselections |
Print selections (Local menu No, Yes) |
Explanation of the formulas being used
Average yield=(Sum achieved/sum planned) *100
Average reject=(Reject/sum planned) *100
Example of a calculation
Let us consider the following elements on the CH1 work center
On the analysis period, the nominal capacity of CH1 is 95 hours.
WO1 | WO2 | WO3 | |
Planned set-up time (hours) | 2 | 5 | 3 |
Operating time (hours) | 12 | 35 | 23 |
Planned parts | 125 | 250 | 310 |
(fixed time)
Total planned quantity: 685 pieces
Production data
WO1 | WO2 | WO3 | |
Correct achieved parts | 110 | 245 | 305 |
Rejected parts | 5 | 6 | 4 |
Achieved parts | 115 | 252 | 309 |
Actual quantity: 115 + 252 + 309 = 676
Rejected quantity: 5 + 6 + 4 = 16
Correct achieved quantity: 110 + 245 + 305 = 660
Average yield: (660/685)*100 = 96,35 %
Average reject: (16/685) = 2,33 %