This function is used to shift in time the production operation selection.

Only "waiting" operations, scheduled and running on a work centre of the type machine or labor are processed.

If a shift is entered, it is applied to the start date for the operation concerned, the new start date loads the forced start date for the operation.

Each Works Order (WO) concerned by the process is de-scheduled then re-scheduled.

Pre-requisites

SEEREFERTTO Refer to documentation Implementation

Screen management

This function is carried out in two steps:

  Selection if the WOs to be processed

  Result of the process

Entry screen

Selection entry

Here this is the entry of a group of criteria that are used to select the operations to be moved:

The production site : it is loaded by default with the production site associated with the operator,

It is possible to choose the status of the WOs to be processed : planned or firm,

The selection of the start/end range.

The following must be entered :

either a shift to be applied in calendar days: the movement can be positive or negative.

or a new start date.

It is possible to specify if the operation dates must be forced by maintaining the initial scheduling of the previous and next operations.

The use of the button is used to start the process.

Results of the process

A report on the processing appears when the date shift is complete, it contains the operations that have been changed and their new start and end dates.

A message warns the user if a selected order could not be processed.

Batch task

This function can be run in batch mode. The standard task FUNMAUTO is provided for that purpose.

Error messages

In addition to the generic error messages, the following messages can appear during the entry :

No works order processed

This message is displayed if no shift could be carried out.

No selection entered, do you want to continue?

Confirmation request if no entry.

Tables used

SEEREFERTTO Refer to documentation Implementation