Shop floor tracking
The Shop floor tracking (SFT) workbench is the main access page for you to track your shop floor activity. This includes clock in and out (if required), going on breaks, recording labor setup and run times, production tracking, elapsed labor, and indirect tasks.
The SFT workbench can also track shop floor activities for Summary and Detailed teams. See Working as a team for more information.
Enter your Employee ID and Site to begin. If you have a default site, it appears when you enter your ID. Available actions and activities are based on your employee profile and your site.
After entering your Employee ID, you can click Defaults to modify your current default settings to filter results for activities. When you click Defaults from this page, you can update your Site, Work center group, and Work center.
If the site you are working on requires clocking in, you need to click Clock in/out to enable all available actions.
If the site does not require clocking in, all available actions are enabled when you enter your Employee ID.
Open activities gridYou can add activities to the grid using the following actions:
Actual labor – Add Setup and Run activities with specific start and stop times. (See Actual labor help.)
Break – Go on a manual break, which adds the break to the grid and stops all open activities. (See Break help.)
Indirect – Add exclusive and nonexclusive activities. (See Indirect help.)
For Run and Setup activities, you can see the related Work order status by clicking Work order status from the Actions icon menu at the beginning of the row.
If there is text for the work order or operation, a Text icon is displayed in the first or second column of the row. Click the icon to read the note.
Employee ID fieldEnter your employee ID.
Site fieldIf you have a default site, it appears when you enter your ID. Or you can enter or select a valid production site. You can change your default site on the Defaults page.
Clock in/out action
If the site you are working on requires clocking in, click Clock in/out to begin or end your shift. When you Clock in, the Clocked in field displays the date and time.
To clock out, click the Clock in/out action. All your Open activities automatically stop.
Prerequisites
Refer to documentation Implementation
Working as a team
If you the Summary team leader
You can track activities for the team like a single employee using the Summary team Employee ID.
You make all entries in the SFT workbench and follow the same procedures as an individual. This also applies to Defaults, Breaks, Indirect labor, and Elapsed labor that behave as for an individual.
You can update the number of team members on the fly from the Adjust team page without stopping or starting activities. Updating the number of employees for an existing team does not affect unposted activities. All open summary team transactions close and reopen with the new summary team count.
If you are part of a Detailed team
You must clock in and clock out as an individual. You can work on team tasks and on tasks outside the team.
You can work on team tasks if you are:
- Clocked in
- Not currently on an exclusive indirect task or a break
- Not currently on a non-team related task
- As an individual, you can also track tasks in SFT workbench without leaving the team.
- You can go on break alone. When you stop your break, you can restart the team labor task to re-join the team activity tracking from the Join team action.
- You can stop working on (suspend) a team-related task before the rest of the team and start an individual activity.
- Note: You cannot work on individual tasks if you are still working on a team-related activity. You must stop work on the team-related activity first.
If you clock in using the Detailed team ID
- You can manage team-related tasks when you log in with the Detailed team Employee ID. When logged in with the Team Employee ID, Defaults, Breaks, Indirect labor, and Elapsed labor behave as for an individual.
- You can:
- Start and stop Run and Setup activities for team tasks
- Enter details when stopping a Run activity for the team such as Completed qty., Rejected qty., and Rejection code
- Put the entire team on break start/stop
- Put the entire team on Exclusive indirect activities
Screen management
Entry screen
Use these fields to create a new employee profile.
Employee
Employee ID (field EMPNUM) |
Enter the Employee ID. For teams, enter the Employee ID for the team. Detailed teams: members must clock in individually. Summary teams: clock in is not required and depends on the Site. |
Site (field FCY) |
If you have a default site, it appears when you enter your ID. Or you can enter or select a valid production site. You can change your default site or the default site for a Detailed team on the Defaults page. Note: Changing the default site for a Detailed team on the Defaults page does not change the default site for team members. |
Clocked in (field CLOCKINFO) |
If your site requires you to clock in, this field displays the date and time you clocked in. If you are part of a Detailed team, you need to clock in individually. |
Grid Open activities
Select (field SELLIN) |
Select this check box to select the activity. You can select multiple activities. |
WO (field WONOTE) |
If there is text for this work order, a Text icon is displayed for this record. Click the icon to read the text. |
Op. (field OPNOTE) |
If there is text for this operation, a Text icon appears for this record. Click the icon to read the text. |
Type (field SFTTYP) |
This field shows the activity type: Run, Setup, Break, etc. |
Document (field VCRNUM) |
This field displays the document number for Work orders. For Indirect activities and Breaks, this field displays the Description for the code.
|
Op. (field OPENUM) |
This field displays the operations number. |
Start date (field STRDAT) |
This field displays the activity start date. |
Start time (field STRTIM) |
This field displays the activity start time. |
UOM (field OPEUOM) |
This field displays the operation unit of measure (UOM). |
Completed qty. (field CPLQTY) |
For Run activities, enter the quantity completed. |
Rejected qty. (field REJCPLQTY) |
For Run activities, enter the rejected quantity when the completed quantity is more than 0. You cannot enter a value greater than the quantity completed. |
Rejection code (field SCANUM) |
Enter a rejection code to provide an explanation for the rejected quantity. |
Closed (field CLEFLG) |
Select the Closed check box to close an operation. For Run activities, complete the following fields as needed: For Detailed team activities, this is performed by the team lead under the team Employee ID.
When the planned quantity for an operation is complete, this check box is automatically selected. |
Work order status |
For Run and Setup activities, you can see the related Work order status by clicking Work order status from the Actions menu at the beginning of the row. |
Actions
Actual labor
Click Actual labor to select and start activities on the Actual labor page. Block number 1
Criteria
Grid Activity
|
To go on a break, click Break and select the appropriate Break code from the list. Only Indirect references with the Category type Break are included in the list.
A break is always an exclusive activity.
For Detailed teams
The team lead, clocked in under the team ID, can manage breaks for all members.
If you are part of a Detailed team and take a break, you leave the team. When you stop your break, you need to click Join to rejoin the team.
Grid
Select (field SELLIN) Select this check box to select the activity. You can select multiple activities.
Code (field COD) This field displays the Break or Indirect reference code.
Description (field DES) This field displays the Break or Indirect reference description.
Click Elapsed labor to enter the time to complete an activity and the quantity produced. This is only available for Setup and Run operations.
Block number 1
Employee ID (field EMPNUM) |
Enter the Employee ID. For teams, enter the Employee ID for the team. Detailed teams: members must clock in individually. Summary teams: clock in is not required and depends on the Site. |
Site (field FCY) |
If you have a default site, it appears when you enter your ID. Or you can enter or select a valid production site. You can change your default site or the default site for a Detailed team on the Defaults page. Note: Changing the default site for a Detailed team on the Defaults page does not change the default site for team members. |
Criteria
Work order (field MFGNUMF) |
This field allows you to filter results in the grid by Work order. |
Operation (field OPENUMF) |
This field allows you to filter results in the grid by Operation. |
Work center group (field WCRF) |
This field allows you to filter results in the grid by Work center group. |
Work center (field WSTF) |
This field allows you to filter results in the grid by Work center. |
Start date (field LSD) |
This field allows you to filter results in the grid by Start date. |
Grid Activity
Select (field FLGL) |
Select this check box to select the activity. You can select multiple activities. |
WO (field WONOTE) |
If there is text for this work order, a Text icon is displayed for this record. Click the icon to read the text. |
Op. (field OPNOTE) |
If there is text for this operation, a Text icon appears for this record. Click the icon to read the text. |
Work order (field MFGNUM) |
This field displays the work order number. |
Op. (field OPENUM) |
This field displays the operations number. |
Activities (field NUMJOBS) |
Enter the number of activities you were doing while performing the activity to track multi-tasking. |
Machine included (field NUMMAC) |
This field displays the number of machines. |
Work center (field CPLWST) |
This field displays the Work center for the activity. You can enter or select another Work center or click Defaults to change your default Work center.
|
Labor center (field CPLLAB) |
This field displays the Labor work center for the activity. You can enter or select another Labor center work center or click Defaults to change your default Labor work center group.
|
Setup duration (field SETDURTIM) |
Enter the total amount of elapsed time spent on the activity. |
Run duration (field RUNDURTIM) |
Enter the total amount of elapsed time spent on the activity. |
Time unit (field TIMUOMCOD) |
This field displays the time unit based on the work order operation. |
UOM (field OPEUOM) |
This field displays the operation unit of measure (UOM). |
Remaining qty. (field REMQTY) |
For Run activities, this field displays the remaining quantity. |
Completed qty. (field COMPLQTY) |
For Run activities, enter the quantity completed. |
Rejected qty. (field REJQTY) |
For Run activities, enter the rejected quantity when the completed quantity is more than 0. You cannot enter a value greater than the quantity completed. |
Rejection code (field REJCOD) |
Enter a rejection code to provide an explanation for the rejected quantity. |
Close (field CLEFLG) |
Select the Closed check box to close an operation. For Run activities, complete the following fields as needed: For Detailed team activities, this is performed by the team lead under the team Employee ID.
When the planned quantity for an operation is complete, this check box is automatically selected. |
Start date (field OPESTR) |
This field displays the activity start date. |
End date (field OPEEND) |
This field displays the activity end date. |
Operation description (field OPEDESC) |
This field displays a description of the operation. |
Work center group (field WCGRP) |
This field displays the Work center group. You can enter or select another Work center group.
|
Labor work center group (field LCGRP) |
This field displays the Labor work center group. You can enter or select another Labor work center group.
|