Scheduling - Implementation
Prerequisites
General parameters
The following general parameters may change the way the function is working :
Manufacturing
DEFDIH (defined at level Site) : Default schedule
OPEEFFAPP (defined at level Site) : Efficiency application
SCHEDWPO (defined at level Site) : Schedule wait and post-op time
WSTEFFINH (defined at level Folder) : Work center efficiency history
Authorizations
An authorization can be granted for this function to limit the processes to a company or a site.
Tables used
The following tables are implemented by the function :
Table |
Table description |
---|---|
MFGHEAD [MFG] |
|
MFGITM [MFI] |
Work orders - products |
MFGMAT [MFM] |
Work order - materials |
MFGOPE [MFO] |
Work order - operations |
OPERATIONS [OPS] |
Load in progress |
ORDERS [ORD] |
WIP |
SCHEDULING [SCH] |
Work order scheduling |
WORKLOAD [WKL] |
Production load |