This function can be launched on a single WO or on a selection of WOs, using the filters.
It is used to calculate the various costs corresponding to the various stages of the WO in order to analyze the variances and the valuation choices in the production reporting.

These different costs are the following:

Provisional theoretical cost: This corresponds to the standard cost but calculated for the provisional production quantity. This cost is also included on the Production cost detail in the Planned column when the standard data is chosen as the Variance calculation source.

Provisional release cost: This is the planned cost with respect to the WO data. It is equivalent to what is included in the Production cost detail in the Planned column when the WO data is chosen as the Variance calculation source.

Provisional production costs: This cost is similar to the provisional release cost but is calculated using the actual quantity produced.

The theoretical planned costs and the planned release cost serve to value the production reporting (according to the general setup CSTRCPORD). They are calculated either on demand or automatically during the creation and/or modification of the WO (according to the CLCWOCAUT setup). The Provisional production cost can only be calculated for a completed WO.

A print-out can be requested at the end of the calculation (see the Production cost calculation detail report)

A certain number of inquiries are used to understand the production cost and provisional cost history for a product, to compare the production cost with respect to the other cost types for the site or another site (see theCost comparison , Production cost history, Production cost inquiry documentation).

 

Prerequisite

SEEREFERTTO Refer to documentation Implementation

Screen management

This function is composed of a screen that is used to assign the selection criteria and the different calculation setups.

Entry screen

Selection criteria

It is necessary to specify a site, to indicate a filter criterion (closed or open WO), then indicate a works order.

A tunnel from the Works order field is used to make a selection of closed WOs or to access a selection following on from a filter.

Calculations

 Cost type: In this section, the cost type that is to be calculated is specified.

 Overhead column choice

By default, the choice displayed corresponds to the choice specified by the OVECOLMFC setup. The choice of column determines the type of overhead cost used.

 Update

Either update the cost calculated during the release or make a simple simulation.

 Print choice

This setup is used to indicate the print type required at the end of processing.

None: No print-out will be released at the end of processing

Detailed: A print-out showing the most detailed level of the calculation will be printed

Summary: A print-out summarizing the calculation will be printed.

 

Batch task

This function can be run in batch mode. The standard task CALMFGCOST is provided for that purpose.

Error messages

The only error messages are the generic ones.

Tables used