Subcontract consumption
This inquiry is used to recapitulate all the materials consumed in sub-contracting orders, for a given purchasing site.
The inquiry can concern all the sub-contracted products or only those corresponding to the selection criteria entered:
- either in the header of the screen (order number range, sub-contracted product range, component product (materials) range, delivery dates,
- or on the window that can be accessed via the button , from which it is also possible, using the buttonto recall an existing setup previously saved under a Memo code. 
Prerequisite
                                                                
 Refer to documentation  Implementation
Screen management
Header
The header information is used to specify the principal selection criteria for the inquiry used.
Selection
| Order site (field POHFCY) | 
| 
                                                                                             The order site is a mandatory field. By default, it is fed with the order site associated to the user. It can be modified by another site authorized for the operator, depending on their authorizations.  | 
                                                                                    
| From subcontract order (field NUMDEB) | 
| 
                                                                                             Start and end ranges used to select the sub-contracting orders to process according to their references.  | 
                                                                                    
| To subcontract order (field NUMFIN) | 
| From subcontracted product (field ITMREFDEB) | 
| 
                                                                                             Start and end ranges used to select the sub-contracting orders to process according to the reference of the released product.  | 
                                                                                    
| To subcontracted product (field ITMREFFIN) | 
| From material (field CPNITMDEB) | 
| 
                                                                                             Start and end ranges used to select the sub-contracting orders to process according to the reference of the sub-contracting product (service).  | 
                                                                                    
| To material (field CPNITMFIN) | 
Start - end range
Tab Sub-con replenishment
By default this table displays a line by materials for each sub-contract order for the chosen selection criteria, showing the following:
- the reference of the material,
 - the delivery date,
 - the required quantity,
 - the consumed quantity,
 - The reference of the sub-contractor,
 - the available sub-contracting quantity.
 
Grid
| Subcontract order (field SCONUM) | 
| 
                                                                                             This field displays the reference of the selected sub-contracting order and cannot be modified.  | 
                                                                                    
| Subcon. product (field ITMREF) | 
| 
                                                                                             This field displays the reference of the sub-contracted product and cannot be modified.  | 
                                                                                    
| Material (field CPNITMREF) | 
| 
                                                                                             This field displays the reference of the service necessary to the realisation of the sub-contracted product and cannot be modified.  | 
                                                                                    
| Major version (field ECCVALMAJ) | 
| Minor version (field ECCVALMIN) | 
| Delivery date (field DLVDAT) | 
| 
                                                                                             This field displays the delivery date for the sub-contracted product and cannot be modified.  | 
                                                                                    
| Requirement qty. (field RETQTY) | 
| 
                                                                                             This field displays the required quantity and cannot be modified.  | 
                                                                                    
| Consumed qty. (field USEQTY) | 
| 
                                                                                             This field displays the used quantity and cannot be modified.  | 
                                                                                    
| Subcontractor (field BPRNUM) | 
| 
                                                                                             This field displays the reference of the supplier of the selected sub-contracting order and cannot be modified.  | 
                                                                                    
| Stock unit (field STU) | 
| 
                                                                                             This field indicates the product management unit in which are expressed: 
 This information is always displayed, regardless of the transaction used. It cannot be modified.  | 
                                                                                    
| Sub-contracting order | 
| 
                                                                                     This button allows a tunnel to the sub-contracting order management function.  | 
                                                                            
Specific Buttons
| 
                                                                         Criteria  | 
                                                                    
                                                                         This button is used to open a window used to enter a certain number of selection and display criteria. This setup can be saved, using the button, under an identification code. it can thus be recalled in a later inquiry. It is thus possible: 
  |