Costing >  Subcontract costs >  Production cost inquiry  

Display all Hide all

This inquiry is used to obtain, for a subcontract order and a released product, the breakdown by cost type of the production cost price for the EO being viewed.

This inquiry is only available if the Production Cost Price has been updated.

Prerequisite

SEEREFERTTO Refer to documentation Implementation

Screen management

The inquiry screen is used to display for each cost group the production cost price for this WO as well as the calculation parameters used .

Header

Presentation

The header is used to enter the selection criteria.

Close

 

Fields

The following fields are present on this tab :

Block number 1

Reference of the manufactured/sub-contracted product which cost price needs to be calculated.

This field contains the storage and/or production site. It is initialized by default with the normal storage site of the user.

  • Year (field YEA)

 

 

  • field VCRNUM

Work order/sub-contract order numbers used to select a cost price.
This number is followed by the line number of the release product.
The line number corresponds to the range of the released product in a multiple works order/sub-contract order, in case of a multiple release.
First range: 1000, second range: 2000, etc.

  • Line no. (field VCRLIN)

 

  • Major version (field ECCVALMAJ)

 

  • Minor version (field ECCVALMIN)

 

  • Order status (field MFGSTA)

 

 

Block number 2

 

  • Product status (field ITMSTA)

 

  • Cost group (field BRDCOD)

 

Block number 3

  • Date calculated (field MFCDAT)

 

 

Block number 4

  • Ratio (%) (field CPLRIO)

 

  • Calculation quantity (field QTYSTU)

 

 

  • Planned quantity (field EXTQTY)

 

 

  • Actual quantity (field CPLQTY)

 

 

Close

 

Tab Production cost price inquiry

Presentation

This tab presents the different cost components of the subcontract order as well as the parameters used for its calculation.

Close

 

Fields

The following fields are present on this tab :

$

  • Material (field MATTOT)

 

  • Component (field MATLEV0)

This field contains the value linked to the material directly associated to the nomenclature first level of the product.

  • Machine (field MACTOT)

 

  • Labor (field LABTOT)

 

  • Subcontract (field SCOTOT)

This field displays the subcontract service cost. The price used to value the service is specified by the VLTSCEOEXT - Service value price/planned PC parameter (ACH chapter, COS group).

  • Overhead (field OVETOT)

 

  • Total without overhead (field CSTTOT)

 

  • Total cost (field TOTWITOVE)

 

  • field MFCDET

 

Grid Graph

  • Description (field LBL)

 

  • field CST

 

Display graph

  • Family detail (field DETFLG)

 

  • Material (field MATFLG)

 

  • Machine (field MACFLG)

 

  • Labor (field LABFLG)

 

  • Subcontract (field SCOFLG)

 

  • Overhead (field OVEFLG)

 

  • Total (field TOTFLG)

 

Close

 

Tab Multi-level

Presentation

This graphical representation shows the production cost price breakdown by cost type.

Close

 

Fields

The following fields are present on this tab :

$

  • Material (field MATTOT)

 

  • Machine (field MACTOT)

 

  • Labor (field LABTOT)

 

  • Subcontract (field SCOTOT)

 

  • Overhead (field OVETOT)

 

  • Total without overhead (field CSTTOT)

 

  • Total with overhead (field TOTWITOVE)

 

  • field MFCDET

 

Grid Graph

  • Description (field LBL)

 

  • field CST

 

Display graph

  • Family detail (field DETFLG)

 

  • Material (field MATFLG)

 

  • Machine (field MACFLG)

 

  • Labor (field LABFLG)

 

  • Subcontract (field SCOFLG)

 

  • Overhead (field OVEFLG)

 

  • Total (field TOTFLG)

 

Close

 

Tab Parameter definition

Fields

The following fields are present on this tab :

Calculation setup

 

 

  • Material (field SLTMATCST)

 

  • Semifinished (field SLTSEMCST)

 

  • Dimension rate (field VLTCCERAT)

 

  • Overhead column (field SLTOVECOL)

 

Close

 

Specific Buttons

This button is used to view the detail of the production cost price by cost group and cost sub-group as well as the detail of the overheads.
The nature button located at the level of the Cost detail screen is used to view the breakdown of the overheads by overheads nature.

This button is used to view the History of the production cost prices for the subcontracting of a product over a given period.

Error messages

In addition to the generic error messages, the following messages can appear during the entry :

Record does not exist

This message appears after entering an EO number if there is no Production Cost Price record corresponding to the 4 identifying elements already entered.

Tables used

SEEREFERTTO Refer to documentation Implementation