The forced synchronization is used to carry out a forced mass synchronization of the out-of-phase records between Outlook and Sage X3.

Screen management

From a single multi-criteria entry screen, a user authorized to carry out the Outlook synchronization can mark the records that need to be submitted to a forced mass synchronization.

Entry screen

As a reminder, the actions implying the display of a record in the synchronization data table are the following:

  • A: Creation (of tasks, calls, appointments and Outlook contacts): a data being created has no precedent.
  • M: Modification. A data being modified has a precedent, it already exists in the base.
  • A: Deletion. The data is no longer present in the database.

The action with the letter "R" means that the current record has been forced.

A data may be forced when there is an anomaly at the level of the current record, for instance; the updating of some information is out-of-phase. Switching the line to status R allows it to be taken into account for the next synchronization.

From the forced synchronization entry screen, the current user can check the object types that they wish to submit to a forced mass synchronization. These can be:

  • the Outlook contacts
  • the tasks
  • the calls
  • the appointments

For each type of object, it is moreover possible to limit the selection by entering record ranges.

As far as the specific case of the forced synchronization of the Outlook contacts is concerned, it is possible to force the records either totally or only in part. It is likewise possible to limit the selection from the contacts of the current sales representative. It is possible to limit the selection depending on a range of sales representatives and/or on a range of information (Leads).

When the processing is started, a detailed log of the results can be sent.

Error messages

The only error messages are the generic ones.

Tables used

SEEREFERTTO Refer to documentation Implementation