This parameter can be defined at Site, Company or Folder levels.

It is used to determine the tolerance percentage accepted for the budget control in amount. The percentage thus specified makes it possible to prevent a lock in case of minor overrun.

Level of localization / Global variable

This parameter is defined at the level Site. It belongs to Chapter BUD (Budgeting) and the Group CMM (Budget control), The following parameters are also associated with this chapter and group :

  • BUDAMT (Budget control by amount)
  • BUDCMM (Include commitments)
  • BUDCMMPRP (Include precommitments)
  • BUDCNTCMM (Commitment control type)
  • BUDCNTPRP (Precommitment control type)
  • BUDCTLPOH (Complete PO budget control)
  • BUDCTLPOL (PO line budget control)
  • BUDCTLPSH (Complete PR budget control)
  • BUDCTLPSL (PR line budget control)
  • BUDPRCQTY (% tolerance - quantity)
  • BUDQTY (Budget control by quantity)
  • BUDTYPCUR (Budget conversion rate type)
  • BUP1 (Controlled budget 1)
  • BUP2 (Controlled budget 2)
  • BUP3 (Controlled budget 3)
  • BUP4 (Controlled budget 4)
  • BUP5 (Controlled budget 5)
  • BUP6 (Controlled budget 6)
  • BUP7 (Controlled budget 7)
  • BUP8 (Controlled budget 8)
  • BUP9 (Controlled budget 9)

No global variable is associated with it.

Functions concerned

The following functions are associated with this parameter :

  Purchasing > Orders > Delivery requests

  Purchasing > Orders > Orders

  Purchasing > Orders > Buyer plan

  Purchasing > Purchase requests > Purchase requests