Apply link qty rounding
This parameter is used in the Cost calculation functions.
It indicates, during the component quantity calculation, if a rounding must be applied to those quantities:
Two values are available:
- No, no rounding applied.
- According to the BOM: roundings are carried out according to the BOM setup.
Example :
Let an end product "ED" and a BOM with two components: CPN1 and CPN2
For 100 EDs, the BOM is as follows:
- CPN1: quantity = 77. Lower rounding and 1 decimal unit.
- CPN2: quantity = 120. Rounding to the nearest and unit with no decimals.
According to the value of this parameter, when applying the calculation to 1 ED, the component quantities will be as follows:
Parameter value |
|
CPN1 |
CPN2 |
No |
|
0.77 |
1.2 |
According to the BOM |
|
0.7 |
1 |
Level of localization/Global variable
This parameter is defined at the level Site. It belongs to Chapter GPA (Manufacturing) and the Group COS (Costs), The following parameters are also associated with this chapter and group :
- CLCBUDRAT (Dimension rate selection bud C)
- CLCCUTRAT (Dimension rate selection act C)
- CLCSIMRAT (Dimension rate selection sim C)
- CLCSTDRAT (Dimension rate selection std C)
- CLCWOCAUT (Auto provisional costs)
- CSTRCPORD (Provisional cost declaration)
- EFFCSTUSE (Efficiency/cost considered)
- MFCRATCPL (Actual PC dim rate selection)
- MFCRATEXT (Expected PC dim rate selection)
- OPRRATE (Labor rate selection)
- OVECOLBUD (Budget calc overhead column)
- OVECOLCUT (Updated calc overhead column)
- OVECOLMFC (PC calc overhead column)
- OVECOLSIM (Simulated calc overhead column)
- OVECOLSTD (Standard calc overhead column)
- SCAMAJ (Material loss increase / costs)
No global variable is associated with it.
Functions concerned
The following functions are associated with this parameter :
Costing > Cost calculations > Budgeted cost calculation
Costing > Cost calculations > Revised cost calculation
Costing > Cost calculations > Simulated cost calculation
Costing > Cost calculations > Standard cost calculation