The objective of this function is to collect the production times and the actual quantities for a given operator.
Unlike the WO tracking function, different types of times can be tracked via an operation workbench: production times spent on an operation for a released work order, production time spent on a routing operation without WO, miscellaneous times.
Refer to documentation Implementation
This function is customized to the needs of your organization and your processes. The transaction you select determines the way in which you enter information and what information is displayed and printed.
If only one transaction has been set up you are not offered a choice, the default entry screen is displayed. The Time tracking plan function contains a header information section into which you enter your selection (or filtering) criteria. The operation tracking details will be built from the reference dates you provide.
Presentation
This section is used to enter the different criteria designed to be used to select all the operations that should be tracked:
Production site: the site for which the tracking is carried out, this field is initialized with the production site associated with the operator.
Personnel ID number: this is the personnel ID number of the operator who enters their times (or for whom the time passed is entered): according to the setup of the transaction, the entry of this personnel ID number is mandatory, optional or forbidden). The personnel ID number entered in the header loads by default the personnel ID number of each line of the operation workbench.
End date range: this is used to select the WO operations where the planned end date falls within the range of the dates entered.
Filter: this is used to select the operations to be tracked depending on their closure flag (closed, not closed, all). According to the transaction setup, the filter is pre-loaded by default and can be entered, displayed or invisible.
Global time: If a global time is entered here, it will be broken down over the different operations of the selection pro rata with the planned times.
WO number ranges: used to set a filter on the work orders to be processed in the operation workbench. This filter is only accessible if the tracking type "WO" is planned by the transaction.
Operation number range : this is used to set a filter on the WO operations to be processed.
Routing/Routing code range: If the user wishes to work without WO and the transaction setup allows it, these fields are used to filter the routings to be processed. In the case where a range of WOs have already been entered in the selection criteria, it is not possible to carryout a selection based on the routes.
Work center: These fields are used to filter the operations (WO or routing) to be processed as a function of their principal work center.
The information shown above makes up the principal selection criteria available to the operator.
This grid is loaded with routing operations or work order operations, according to the selection criteria entered.
All the columns displayed in this grid and their display order depend on the setup of the chosen transaction.
The columns available are a function of the tracking type that it is possible to use with this transaction.
The pre-loading of the production time and actual quantity fields with the planned times and quantities depends on the setup of the chosen transaction.
A WO to be tracked operation can come from the selection criteria or added manually in the grid. The corresponding tracking type is the "WO" tracking.
It is possible to modify the actual work center and the actual labor work center.
According to the transaction setup, it is possible to choose, or not to choose, the tracking unit (amongst which the stock unit for the released product and the operation unit).
The information that can be entered for an operation is as follows:
The posting date: by default the current date is proposed, also it is possible to enter an earlier date than the current date but not a later date.
The actual principal work center and the secondary labor work center
Completed quantity: it is the total quantity completed for the operation, it includes the rejected quantity or the quantity under control coming from the operation. In order to minimize the entry and if the transaction setup allows it, the completed quantity field for each operation is loaded by default with the remaining quantity for the WO and by default the operation closure is proposed.
The rejected quantity
The actual setting time and actual operation time
The ID number (as a function of the transaction setup)
The messages: it is possible to assign a message to an operation tracking, the creation of new messages during the tracking is also possible.
The scrap messages : if a reject quantity is entered on the operation line, it is possible to associate the entry with up to 15 different reject messages, each associated with a part of the total rejected quantity.
Finally, it is possible to add a non-planned WO operation booking by simple entry of the operation in the grid: the system detects that the operation entered is not planned in the referenced WO and a warning message is displayed for user confirmation.
If a tracking range operation is present in the grid, the operations tracked by this range will not be displayed in the grid: their actual quantities and times are automatically adjusted according to the range tracking.
According to the setup chosen for the time tracking plan transaction, it is also possible to enter the time on the basis of a route without WO.
A routing to be tracked operation can come from the selection criteria or be added manually in the grid. This type of tracking corresponds to the "Product" tracking.
The line is then re-loaded with the information coming from the routing operation.
It is possible to associate a BOM and BOM alternative to each operation in the route for which a tracking entry will be made. The system then checks that the routing being tracked is actually a parent routing associated with the selected BOM.
It is possible to add the tracking of a non-planned routing operation by simple entry in the grid of this operation: the system detects that the operation entered is not planned in the referenced routing and warns the user for confirmation.
According to the setup chosen for the operation workbench transaction, it is also possible to enter the production times on the basis of the work centers without either WO or routing.
Such a tracking line is of type "Miscellaneous tracking" and is used to total in a specific work center all the non-productive times of the same nature, for instance.
According to the setup chosen for the operation workbench transaction, it is possible to plan the material consumptions and the stock receipts of finished products automatically and without user intervention.
Only the materials attached (in the BOM) to the tracked operation are consumed.
The materials not attached to any operation are consumed at the time of tracking of the productive operation.
The receipt into stock is performed at the time of the productive operation tracking.
According to the setup chosen for the operation workbench transaction, it is possible to access a manual production reporting.
In this case, the Produced goods action is available on the productive operations. This action provides access to a preloaded production workbench (for which the transaction is then chosen) of the product/products (in the case of a multi-product release or sub-product management) to be received to stock. The receipt to stock is then carried out according to the setup planned by the production workbench that has been activated (see the Production workbench documentation).
After validation of the entries in the Production Workbench, the tracking(s) corresponding to the stock receipt is/are created.
Exiting the production workbench automatically returns the user to the operation workbench as it was before unbranching.
Validating the operation workbench entries creates the corresponding tracking(s), the manual entries already carried out are no longer relevant.
According to the setup chosen for the operation workbench, it is possible to access a manual material consumption.
In this case, the Material consumption action is available on those operations to which materials are attached. This action gives access to a pre-loaded operation workbench (for which the transaction is then chosen) with the materials to be issued from stock. The material issues then take place according to the setup of the selected consumption workbench (see the Material Issue Workbench documentation).
Exiting the material issue workbench automatically returns the user to the operation workbench such as it was before debranching.
Validating the operation workbench entries creates the corresponding tracking(s), the manual entries already carried out are no longer relevant.
Close
Fields
The following fields are present on this tab :
Filters
|
The production site associated with the user is proposed by default. It can be modified by another site authorized for the operator, depending on its authorizations. |
|
This field corresponds to the Labor operator. |
|
  |
|
This field makes it possible to filter the data to be processed. |
|
  |
|
Use this field to filter the records to be tracked. Select one of the following values:
|
Start - end range
|
Entering these fields is not mandatory. Use them to limit the display of allocations to one document or a range of documents. |
|
Enter the selection end entry number. |
|
Enter the selection start operation number. |
|
Enter the selection end operation number. |
|
Enter the selection start product number. The product ranges limit the adjustment to these products only. |
Enter the selection end product number. |
|
Enter the selection start routing. |
Enter the selection end routing. |
|
Enter the start selection routing code. |
Enter the end selection routing code. |
|
Enter the name of the initial work center of the selection. |
|
Enter the name of the final work center of the selection. |
Block number 2
|
If a global time is entered here, it will be broken down over the different operations of the selection pro rata with the planned times. |
|
The time unit makes it possible to express the time in hours and minutes. |
|
  |
|
This is the date which is used when posting the movement. It defaults to today's date but can be changed to an earlier date, if the selected date is in an open period in the accounting calendar.
|
|
This field can take the following values:
|
|
This field displays the work order number (unique ID). |
|
The routing is used to describe the product manufacturing process. |
|
Multiple routings can be defined for a single product. Each routing code can be assigned specific management features. These include restriction of the routing to a specific site and to specific areas of functionality (for use in a manufacturing environment, for costing or for capacity planning). |
|
|
|
Several BOMs can be defined for the same product reference. The various BOM codes can be used to manage different product structures according to their use context such as:
This field can be left empty (value = 0) to enable manual entry of the components. In this case, only the component is loaded. |
|
The production routing is described by means of operation numbers. |
|
This field indicates the routing operation. |
|
The standard operation is a "template" operation used to create or modify the routing operations. Recover the standard operation data:
|
|
This field indicates the actual work center. |
|
A labor work center can be associated with the machine-type principal work center. The labor work center times are calculated using two coefficients:
|
|
This is the planned setting time to obtain the setting time allocated to the labor work center linked to the main work center. This coefficient applied to the planned setting time to obtain the setting time allocated to the labor work center linked to the main work center. |
|
This is the coefficient applied to the planned operation time. It is used to obtain the operation time for the labor work center linked to the principal work center. This field is only available for entry if the labor work center is defined. Operation times are subdivided as follows: Proportional times are expressed for the production of an operation unit (and not in the stock unit of the finished product using the routing). |
|
The operation unit expresses the operating time in another unit than that of the product described by the routing. Example :
This unit is associated with a conversion coefficient for the stock unit of the product for which the routing has been set up and the operation unit. The quantities of the work order operations are expressed in the operation unit. |
|
  |
|
  |
|
This field displays the total completed quantity, including the rejected quantity, expressed in the operation unit. |
|
This field displays the actual rejected quantity.
|
|
The time unit defines how time for the operations in this routing is expressed. The time unit can be 'hours' or 'minutes'. It applies to the setup time, run time and the rate of all operations in the routing. |
|
This is the actual setting time. |
|
  |
|
This is the actual operation time. The operating time:
|
|
Use this field to specify whether the line must be closed or not ('Yes'/'No'). |
|
This field corresponds to the Labor operator. |
|
This field displays the information message linked to the operation tracking. |
|
It is the information message concerning the rejected quantity. |
|
  |
|
  |
The setup determines whether the analytical dimensions can be modified. These are initialized in compliance with the default dimension setup.
In creation mode, as in modification mode, if an order line has been entered and the project code is modified, analytical dimensions are not reset. |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
  |
Close
Action icon
Click Popup view from the Actions icon to view the information for this operation using the standard screen display mode.
Click Technical sheet from the Actions icon to assign or view the technical sheet linked to this operation if planned in this work order.
Click Work Order from the Actions icon to view the work order details.
Click Operation detail from the Actions icon to view the details for this operation.
Click Tracking status from the Actions icon to view the current tracking status of this operation. The Operation quantities screen summarizes the planned, actual and remaining quantities and times.
Click Material consumption from the Actions icon to view the material consumption for this work order.
Click Produced goods from the Actions icon to view the production details including the material consumption for this work order.
Click Text from the Actions icon to view, enter or modify text associated with this operation. For example, information describing how to use the workstation, how to merge colors, how to use tools, the torsional movement to fix a screw.
Close
Click the Search action to load the grid with the operations to be tracked according to the entered selection criteria. You can delete selected lines (click Delete from the Actions icon) and add new lines to the grid. The maximum number of lines available is defined in the selected entry transaction. |
Click the Transaction action to view or amend the format of this entry transaction.
In addition to the generic error messages, the following messages can appear during the entry :
The messages that arise from the manual tracking of materials or the manual production reporting are listed in the corresponding documentation (Material tracking plan, Production plan).
This message is displayed when creating the tracking for a work order where a material is out of stock, the Release if shortage setup is set to 'No' in the product-site record and the MTKALLMGT general setup Mandatory allocation to the WO is set to 'Yes'.
This message is displayed if the status of the work order is not set to 'Firm'.
This message is displayed if the work order is not at a minimum allocated globally and the MKTALLMGT general setup, Mandatory allocation to the WO, is set to 'Yes'.
This message is displayed if the production folder has not been printed and this is mandatory for production to start (according to the DOSFAB general setup).
This message is displayed if the work order is not complete (only materials or only operations) and the WO management plans to complete this order before releasing the production.
This message is displayed when an attempt is made to track an operation even though the previous operation has not been tracked. This message can be blocking or not according to the value of the CTLOPEPRE general setup. This message only concerns trackings of type "WO".
This message is displayed upon tracking creation (as a function of the value of general setup CTLFICTEC) and if an operation with a technical sheet has been tracked and that the technical sheet has not been entered.
This message is displayed when adding a non-planned operation of the sub-contractor type (entry of a standard sub-contractor operation or an actual work centre of the type sub-contractor).
This warning message is displayed during the tracking of an operation if the actual quantity is greater than the planned quantity.
This message is displayed during operation tracking if the rejected quantity is greater than the actual quantity.
This message is displayed during the addition of a non-planned operation based on a standard operation.
This message is displayed during the manual tracking of an operation if the actual labour work centre is identical to the actual principal work centre.
This message can be displayed following the validation control on the actual labour work centre.
This message can be displayed following the validity control on the actual machine or labour work centre.
This warning is displayed if this work order uses a routing that is version-managed and you have chosen to modify an existing operation. Click Cancel to abandon your action. To modify the work center, click OK. You will not be prevented from modifying the operation if you need to.
This message is displayed during the validation of the BOM code in the case of a "Product"-type tracking.
This warning is displayed if this work order is for a product (BOM) that is version-managed and you have chosen to add a new component to it. Click Cancel to abandon your action. To add the new component, click OK. You will not be prevented from adding the component if you need to.
Information message if a second attempt is made to manually track the materials linked to an operation.
Information message if a second attempt is made to manually report the production of products linked to an operation.
This warning is displayed if this work order uses a routing that is version-managed and you have chosen to add a new operation to it. Click Cancel to abandon your action. To add the new operation, click OK. You will not be prevented from adding the operation if you need to.
This message is displayed if an attempt is made to add an operation that already exists on another line.
Work center does not exist for this site.
This message is displayed if an attempt is made to track an operation for which the tracking stage field (no, normal, range) is set to no.