Set by-product low level code

Use this parameter to define when the Material Requirements Planning (MRP) and Master Production Schedule (MPS) calculations need to process the by-products or secondary products included on a work order that are produced during the main manufacturing process.

Yes: Process by-products before finished products. This ensures extra suggestions are not created for by-products.

No: Sage advises that you do not set this parameter value to No.

Level of localization/Global variable

This parameter is defined at the level Site. It belongs to Chapter STO (Inventory) and the Group SCH (Planning). The following parameters are also associated with this chapter and group:

No global variable is associated with it.

Functions impacted

The following functions are associated with this parameter:

  Manufacturing > Planning > MPS processing

  Stock > Reorders > MRP processing

  Manufacturing > Planning > MRP processing

Comments

The type of suggestions to be generated (work order, purchase order, intersite transfer, or subcontract order) are defined in the MRP Requirements parameters (Setup > Stock > Requirements parameters (GESPCB)).