Planner/buyer filter
This parameter controls access to reordering based on who manages a product.
The notion of 'planner' and 'buyer' must be considered when a product needs reordering (a 'buyer' is a person who can raise firm purchase orders for a product). For any given product and/or site (product-site) this parameter can be used to filter by who manages the product (the Planner) and who is in charge of reordering the product (the Buyer).
'None' - Do not filter the planning workbenches – Enterprise planning, Grouping and the product Planning workbench – or the Work order and Purchase order management functions by Sage X3 user.
'Nonexclusive filter' - Filter the planning workbenches and the Work order and Purchase order management functions for those products where the Sage X3 user is defined as the Planner/Buyer for the product/product-site and the Planner/Buyer is blank.
'Exclusive filter' - Filter the planning workbenches and the Work order and Purchase order management functions for those products where the Sage X3 user is defined as the Planner/Buyer for the product/product-site.
Level of localization/Global variable
This parameter is defined at the level Folder. It belongs to Chapter STO (Inventory) and the Group SCH (Planning), The following parameters are also associated with this chapter and group :
- AVGDAY (Average days per month)
- AVGWRKDAY (Average work days per month)
- DEFPTO (Assignment rule MTO)
- FIRWRKDAY (First work day of week)
- GPLNHOR (Default planning horizon)
- MPSECCSOF (Process firm SOs in MPS)
- MPSECCSOP (Process planned SOs in MPS)
- MPSECCSOS (Process suggested SOs in MPS)
- MPSPJTSOF (Process firm SOs in MPS)
- MPSPJTSOP (Process planned SOs in MPS)
- MPSPJTSOS (Process suggested SOs in MPS)
- MPSRECOVST (MPS reduce coverage stock)
- MPSSECCOV (Safety stock coverage)
- MRPECCSOF (Process firm SOs in MRP)
- MRPECCSOP (Process planned SOs in MRP)
- MRPECCSOS (Process suggested SOs in MRP)
- MRPPJTSOF (Process firm SOs in MRP)
- MRPPJTSOP (Process planned SOs in MRP)
- MRPPJTSOS (Process suggested SOs in MRP)
- MRPRECOVST (MRP reduce coverage stock)
- MRPREOALL (Exclude transfer allocation)
- MRPSECCOV (Safety stock coverage)
- PLNTWD (Weekly planning structure)
The global variable GPLNFLT is associated with it.
Functions impacted
The following functions are associated with this parameter :
Manufacturing > Planning > Planning workbench
Purchasing > Supply > Planning workbench
Manufacturing > Planning > Enterprise planning
Purchasing > Supply > Enterprise planning
Manufacturing > Planning > Grouping
Purchasing > Supply > Grouping workbench
Manufacturing > Planning > Work order
Manufacturing > Planning > Multi-level planning