Modify objectives
Use this function to change the target production dates for one or a range of scheduled work orders at a given production site.
You can change target production dates (objective dates) if your objectives or requirements for a work order have changed, or you are aware of an issue that might delay (or advance) production.
Prerequisites
Refer to documentation Implementation
Screen management
There are two screens in this function. Use the first screen to select the works orders to be processed; use the second screen to adjust dates and priorities for the selected work orders.
A log file displays the results of the run.
Entry screen
For a specified production site, select the types of work orders to be included in the run.
Start/end ranges
A number of ranges are displayed.
- To include all applicable work orders, leave all the fields blank.
- To include only selected work orders, type in the required ranges. Leave the first field blank to include the lowest value.
Block number 1
Production site (field MFGFCY) |
Type in or select the production site from which the work orders are to be selected. This field is mandatory. |
Filters
Firm work orders (field WOFFLG) |
Select this check box if firm work orders are to be processed. If firm work orders are to be excluded from the run, leave this check box clear. |
Planned work orders (field WOPFLG) |
Select this check box if planned work orders are to be processed. If planned work orders are to be excluded from the run, leave this check box clear. |
Include optimized orders (field OPTFLG) |
Click this check box if optimized work orders are to be processed. If optimized work orders are to be excluded from the run, leave this check box clear. |
Start - end range
Order no. (field MFGNUMDEB) |
Filter for results within a range of work orders. For a single work order, enter the same work order number in the from/start Order no. (Work order number) and to/end Order no. fields. |
Project (field PJTDEB) |
Filter for results within a range of project codes. For a single project, enter the same project code in the From/start project and To/end project fields. If the value of this field includes a character such as an exclamation mark "!" this field links to the structure of the project. The character is the separator between a project code and the structure, either the project budget structure or the project operational (task) structure. For example, if a material task code is "USA-P3" and a project code is "USA12345678", this field displays a link to the project operational structure as "USA12345678!USA-P3".
|
Destination (field BPCNUMDEB) |
Filter for results within a range of "ship-to" customers and/or sites. For a single customer or site, enter the same code in the from/start Destination and to/end Destination fields. |
Order no. (field VCRNUMDEB) |
Filter for results within a range of source sales orders. For a single sales order, enter the same code in the from/start Order no. (Order number) and to/end Order no. fields. |
Released product (field ITMREFDEB) |
Filter for results within a range of finished products (BOMs). For a single bill of materials (BOM), enter the same product code in the from/start Released product and to/end Released product fields. |
Start date (field STRDATDEB) |
Filter for results within a range of dates. For a single day, enter the same date in the Start date and End date fields. You can leave the Start date field blank to search all records to date. |
Sort criteria
field TRI |
Use this field to modify the sort order. |
Tab Search results
This screen displays all scheduled work orders at the specified site that meet the defined selection criteria. The outstanding quantities for each work order line are included.
Block number 1
Production site (field MFGFCY) |
The production site from which the work orders are to be processed. |
field FCYDES |
The name (title) of the production site. |
No. W.O. (field MFGNUM) |
This field displays the work order number. |
Order status (field MFGSTA) |
This field indicates the current status of the work order to be generated. This status can be 'Firm' or 'Planned'. You cannot modify it. |
Status (field MFGTRKFLG) |
The Allocation (materials), Scheduling and Status fields display a status for this work order. These fields are updated automatically by the system. The current status, or progress of this work order is displayed in the Scheduling and Status fields. Selected combinations to note are as follows:
The work order allocation values are defined in Local menu 336. For detailed scheduling, Activity code POPS activates the Production Scheduler functionality or the Generic finite scheduler interface.
|
Routing (field ROUNUM) |
Routing code (field ROUALT) |
Multiple routings can be defined for a single product. Each routing code can be assigned specific management features. These include restriction of the routing to a specific site and to specific areas of functionality (for use in a manufacturing environment, for costing or for capacity planning). |
STK (field STU) |
This field displays the unit in which the product is stored. It provides the key to prices, costs, volumes etc. |
Remaining quantity (field RMNEXTQTY) |
This field displays the remaining (outstanding) quantity required to complete the order. |
Start date (field STRDAT) |
This field identifies the planned production start date for this work order. The date is determined by the Scheduling mode:
You cannot change this date if you use Production Scheduler, that is Activity code POPS-Production Scheduler is 'Active', if the operations on this work order have been optimized by the scheduler.
|
End date (field ENDDAT) |
This field identifies the end or required completion date for this work order. The date is determined by the Scheduling mode:
You cannot change this date if you use Production Scheduler, that is Activity code POPS-Production Scheduler is 'Active', if the operations on this work order have been optimized by the scheduler.
|
Objective date (field OBJDAT) |
This field displays the end date of this work order. It represents a target production delivery date. It is calculated when a work order is created and scheduled for the first time. If your objectives, requirements or target completion date for this work order have changed you can change this date.
|
Early/Late (field AVRT) |
This field measures the number of days between the target production delivery date of this work order (field Objective date) and the end or required completion date for this work order (field End date). It shows a positive figure if the work order will be completed early and a negative figure if the work order is overdue or will be late, according to the scheduling or your planning. |
Priority (field MFGPIO) |
Use this field to assign a priority to this work order. |
Scheduling (field SCDFLG) |
The Allocation (materials), Scheduling and Status fields display a status for this work order. These fields are updated automatically by the system. The current status, or progress of this work order is displayed in the Scheduling and Status fields. Selected combinations to note are as follows:
The work order allocation values are defined in Local menu 336. For detailed scheduling, Activity code POPS activates the Production Scheduler functionality or the Generic finite scheduler interface.
|
Allocation (field ALLSTA) |
Scheduling mode (field SCDMOD) |
This field displays the scheduling mode defined on the Header. 'Backward' scheduling respects the defined End date ; 'Forward' scheduling respects the defined Start date. |
Project (field PJT) |
This field displays the associated project code. The content can be one of the following:
If the content of this field includes a character such as an exclamation mark "!" this field links to the structure of the project. The character is the separator between a project code and the structure, either the project cost structure or the project operational structure. For example, if a material task code is 'USA-P3' and a project code is 'USA12345678', this field displays a link to the project operational structure as 'USA12345678!USA-P3'. To provide a quick and easy visual reference the link to the project or project structure is distinguishable by the number of separator characters used. If there is no separator, the link is made to the project. A single separator character such as an exclamation mark after the project code (the first code) indicates the link type is a task (the link is to the project operational structure). Two separators placed after the project code mean that the link corresponds to a budget code (link to the project budget structure). |
Destination (field BPCNUM) |
This field displays the 'ship-to' customer or site. |
Source document number (field VCRNUM) |
This field identifies the number of the source document or order. |
Work orders |
Click Work order from the Actions icon to view the work order details. The transaction you select determines the way in which you enter information, and what information is displayed and printed. If only one transaction has been set up you are not offered a choice, the default entry screen is displayed. |
Workbench |
Click Workbench from the Actions icon to view the projected stock movements for the selected product. The transaction you select determines the way in which you enter information, and what information is displayed and printed. If only one transaction has been set up you are not offered a choice, the default entry screen is displayed. |
Load in progress |
Click Load in progress from the Actions icon to view the status and progress of the work order operations. |