Provisional Cost Inquiry
This inquiry is used to obtain the breakdown by cost type of the provisional cost price for a given WO and released product.
Prerequisite
Refer to documentation Implementation
Screen management
The inquiry screen displays for each cost group the provisional cost price for this WO as well as the calculation parameters used. It provides a way to view the theoretical provisional costs or the provisional cost at release.
It also displays a graph representing the cost price breakdown by cost type.
The total result is not a result returned for the unit; it is a global result.
Header
Product (field ITMREF) |
Reference of the manufactured/sub-contracted product which cost price needs to be calculated. |
Stock site (field STOFCY) |
Use this field to define the storage and/or production site. The site defined on the user record is displayed by default but can be amended.
|
Year (field YEA) |
Currency (field CUR) |
field VCRNUM |
Work order/sub-contract order numbers used to select a cost price. |
Line no. (field VCRLIN) |
Major version (field ECCVALMAJ) |
Minor version (field ECCVALMIN) |
Order status (field MFGSTA) |
Project (field PJT) |
Product category (field TCLCOD) |
Product status (field ITMSTA) |
Cost group (field BRDCOD) |
Date calculated (field MFCDAT) |
Overhead (field OVECOD) |
Ratio (%) (field CPLRIO) |
Calculation quantity (field QTYSTU) |
field STU0 |
Planned quantity (field EXTQTY) |
field STU1 |
Actual quantity (field CPLQTY) |
field STU2 |
Tab Expected cost inquiry
Block number 1
Material (field MATTOT) |
Component (field MATLEV0) |
This field contains the value linked to the material directly associated to the nomenclature first level of the product. |
Machine (field MACTOT) |
Labor (field LABTOT) |
Subcontract (field SCOTOT) |
This field displays the subcontract service cost. The price used to value the service is specified by the VLTSCEOEXT - Service value price/planned PC parameter (ACH chapter, COS group). |
Overhead (field OVETOT) |
Total without overhead (field CSTTOT) |
Total cost (field TOTWITOVE) |
Detail (field MFCDET) |
Grid Graph
Description (field LBL) |
field CST |
Display graph
Family detail (field DETFLG) |
Material (field MATFLG) |
Machine (field MACFLG) |
Labor (field LABFLG) |
Subcontract (field SCOFLG) |
Overhead (field OVEFLG) |
Total (field TOTFLG) |
Tab Graphic
Block number 1
Material (field MATTOT) |
Machine (field MACTOT) |
Labor (field LABTOT) |
Subcontract (field SCOTOT) |
Overhead (field OVETOT) |
Total without overhead (field CSTTOT) |
Total with overhead (field TOTWITOVE) |
Detail (field MFCDET) |
Grid Graph
Description (field LBL) |
field CST |
Display graph
Family detail (field DETFLG) |
Material (field MATFLG) |
Machine (field MACFLG) |
Labor (field LABFLG) |
Subcontract (field SCOFLG) |
Overhead (field OVEFLG) |
Total (field TOTFLG) |
Tab Parameter definition
Calculation setup
BOM code (field BOMALT) |
Routing code (field ROUALT) |
Material (field SLTMATCST) |
Semifinished (field SLTSEMCST) |
Dimension rate (field VLTCCERAT) |
Overhead column (field SLTOVECOL) |
Reports
By default, the following reports are associated with this function :
MFGCOST : WO cost detail
This can be changed using a different setup.
Specific Buttons
Detail |
Used to view the detail of the cost price by sub-groups. |
Archived |
Used to view theCost price history. |