Task dates adjustment
All Project management tasks have planned start and planned end dates. Project management controls these dates across the various task levels to ensure consistency. As individual task dates can be adjusted both manually and automatically, you use this parameter to define when parent level task date fields should be adjusted to reflect the earliest start date and the latest end date of child level tasks when the start or end date of an operational task, or an employee assignment is adjusted.
On demand update: This is the default value for this parameter. Adjust task start and end dates to reflect the earliest start date and the latest end date of lower level tasks when Adjust task dates is selected from the Actions menu for an individual task, or the Adjust all dates action is selected from the Action panel in the Task planning screen.
Automatic update: Automatically adjust task start and end dates to reflect the earliest start date and the latest end date of lower level tasks.
Level of localization/Global variable
This parameter is defined at the level Site. It belongs to Chapter TC (Common Data) and the Group PJM (Project management), The following parameters are also associated with this chapter and group :
- BILTIMSPLI (Split billable time if needed)
- BILTIMSTA (Billable time status)
- ESTBILINIT (Prog. status percentage init.)
- ESTPRBINIT (Estim. budget progress init.)
- ESTPRGINIT (Estim. project progress init.)
- ESTPRGMET (Bud/proj progress estim method)
- ESTPRGSYNC (Updated est. progress/snapshot)
- ESTPRTINIT (Estimated task progress init.)
- ESTPRTMET (Task progress estim. method)
- ESTREVINIT (Estimated revenue init.)
- ESTREVMET (Revenue estimation method)
- ESTREVSYNC (Updated est. revenue/snapshot)
- FINOVERSYN (Updated fin. status/snapshot)
- GAUPTE (Time entry automatic journal)
- HOURLYUNIT (Hour unit)
- MINUTUNIT (Minute unit)
- OPPDATUPD (Project dates adjustment)
- PCCAUTCRE (Create cost type dimension)
- PCCCOD (Default labor cost type)
- PCCCODDEF (Default cost type)
- PCCCODFIN (Default financial cost type)
- PJMAUSCST0 (Allow time entry costs to 0)
- PJMCST (Employee labor rate priority)
- PJMCSTLAB (Project labor rate priority)
- PJMDATCTRL (Control time entry )
- PJMENDPRD (Allowed end period)
- PJMLOGFIL (Project technical log file)
- PJMOPECST (Operation labor rate priority)
- PJMORDCRE (Create firm order from task)
- PJMORDTRA (Associated orders trans.)
- PJMPLNTRA (Enterprise planning trans.)
- PJMSTRPRD (Allowed start period)
- PJMTIMAUTO (Time entry auto. validation)
- PJMTIMBUD (Allow time entries on budgets)
- PJMTIMENT (Time entry control phase)
- PJMTIMNEG (Allow time entries negative qt)
- PJMTIMTAS (Allow time entries on tasks)
- PJTAUTCRE (Create Projects dimension)
- PJTMGT (Project management)
- POSTPCCDEF (Source of posted labor account)
- POSTRATDEF (Source of posted labor rate)
- PSOREV (Sold product revision mngt)
- PTEFCY (Single / multi-site statement)
- TASBUDAUT (Budget automatic creation)
- UNITWORK (Default unit of labor)
- UPDFCYCCE (Update site on dimension)
- WOPJMMSG (Block multiple projects on WO)
No global variable is associated with it.
Functions impacted
The following functions are associated with this parameter :
Projects > Projects > Project management
Activity codes
The following activity codes (sorted by type) are associated with the parameter :
PJM : Project management