Task progress estim. method
This parameter defines if the estimated progress of a project task is to be entered manually or calculated automatically.
Manual entry or calculated - This is the default value for this parameter. The estimated progress of a task can be entered as a percentage figure manually or it can be calculated automatically by clicking a Refresh icon in the operational structure.
Manual entry - The estimated progress percentage of a task must be entered manually.
Calculated - The estimated progress percentage of a task is calculated automatically by clicking a Refresh icon in the operational structure.
The field associated with this parameter in the operational structure is the Estimated progress (%) field (PRCCPL). If the Estimated progress (%) field is calculated automatically an SQL query compares the sum of consumed load against planned load for the labor task operations to obtain this value.
ESTPRTINIT - Estimated task progress initialization parameter (TC chapter, PJM group). You use this parameter to define the SQL query that is to be executed to initialize the task field each time the estimated task progress percentage is refreshed.
Level of localization/Global variable
This parameter is defined at the level Site. It belongs to Chapter TC (Common Data) and the Group PJM (Project management), The following parameters are also associated with this chapter and group :
- BILTIMSPLI (Split billable time if needed)
- BILTIMSTA (Billable time status)
- ESTBILINIT (Prog. status percentage init.)
- ESTPRBINIT (Estim. budget progress init.)
- ESTPRGINIT (Estim. project progress init.)
- ESTPRGMET (Bud/proj progress estim method)
- ESTPRGSYNC (Updated est. progress/snapshot)
- ESTPRTINIT (Estimated task progress init.)
- ESTREVINIT (Estimated revenue init.)
- ESTREVMET (Revenue estimation method)
- ESTREVSYNC (Updated est. revenue/snapshot)
- FINOVERSYN (Updated fin. status/snapshot)
- GAUPTE (Time entry automatic journal)
- HOURLYUNIT (Hour unit)
- MINUTUNIT (Minute unit)
- OPPDATUPD (Project dates adjustment)
- PCCAUTCRE (Create cost type dimension)
- PCCCOD (Default labor cost type)
- PCCCODDEF (Default cost type)
- PCCCODFIN (Default financial cost type)
- PJMAUSCST0 (Allow time entry costs to 0)
- PJMCST (Employee labor rate priority)
- PJMCSTLAB (Project labor rate priority)
- PJMDATCTRL (Control time entry )
- PJMENDPRD (Allowed end period)
- PJMLOGFIL (Project technical log file)
- PJMOPECST (Operation labor rate priority)
- PJMORDCRE (Create firm order from task)
- PJMORDTRA (Associated orders trans.)
- PJMPLNTRA (Enterprise planning trans.)
- PJMSTRPRD (Allowed start period)
- PJMTIMAUTO (Time entry auto. validation)
- PJMTIMBUD (Allow time entries on budgets)
- PJMTIMENT (Time entry control phase)
- PJMTIMNEG (Allow time entries negative qt)
- PJMTIMTAS (Allow time entries on tasks)
- PJTAUTCRE (Create Projects dimension)
- PJTMGT (Project management)
- POSTPCCDEF (Source of posted labor account)
- POSTRATDEF (Source of posted labor rate)
- PSOREV (Sold product revision mngt)
- PTEFCY (Single / multi-site statement)
- TASBUDAUT (Budget automatic creation)
- UNITWORK (Default unit of labor)
- UPDFCYCCE (Update site on dimension)
- WBSDATUPD (Task dates adjustment)
- WOPJMMSG (Block multiple projects on WO)
No global variable is associated with it.
Functions impacted
The following functions are associated with this parameter :
Projects > Projects > Project management
Projects > Projects > Snapshots > Financial snapshots
Projects > Projects > Utilities > Financial status extraction
Projects > Projects > Utilities > Financial snapshot extraction
Activity codes
The following activity codes (sorted by type) are associated with the parameter :
PJM : Project management